Supply-side bonding jumpers are sized from Table 250.102(C)(1), based on the service or supply conductors. Load-side bonding jumpers are sized from Table 250.122, based on the breaker or fuse ahead of them. Water pipe and building steel bonds also use Table 250.102(C)(1), and the water pipe bond never has to be larger than 3/0 copper. Open your 2020 NEC to Article 250, Part V and follow along.

Try this question with your code book open, then check your answer below. Questions like it are common on electrician license exams and in grounding and bonding CE quizzes.

Practice question: A service is supplied by copper conductors with an equivalent area of 2,500 kcmil per phase. What is the minimum size copper bonding jumper to the interior metal water piping?

  1. 2/0 AWG
  2. 3/0 AWG
  3. 300 kcmil
  4. 350 kcmil
Show the answerHide the answer

The answer: B, 3/0 AWG copper

  • Size the water pipe bonding jumper from Table 250.102(C)(1) (250.104(A)(1)).
  • 2,500 kcmil is over 1100 kcmil, so Note 1 applies: 2,500 × 12½% = 312.5 kcmil.
  • But 250.104(A)(1) says this jumper never has to be larger than 3/0 copper (or 250 kcmil aluminum). 3/0 wins.

The trap is answer D. 312.5 kcmil rounds up to 350 kcmil, and that is the right size for a main or supply-side bonding jumper on this service. The water pipe jumper has its own 3/0 cap.

Want hundreds more questions like this one? JCR's $495 self-study package has 500+ practice questions (digital and printed), 100 video lessons, a 152-page study manual and permanent code tabs. Videos and the digital practice exams open right after you order.

Pick your state's package

Want a live instructor? JCR's live Zoom exam prep class teaches the 2020 NEC in four 4-hour sessions on Tuesday evenings and Saturday mornings, Eastern time, for $800. It fits any exam on the 2020 NEC. Testing in North Carolina? You can also take the two-day in-person class ($845) in Raleigh, Asheville, Mooresville (Charlotte area) or Winston-Salem. 93% pass rate for JCR classroom students.

See live Zoom class dates

See NC class dates

The rule

Every bonding jumper gets its size from one of two tables. The question is which side of the overcurrent device it sits on.

  • Supply side (no overcurrent device ahead of it): use Table 250.102(C)(1), based on the largest ungrounded supply conductor (250.102(C)(1)).
  • Load side (after a fuse or breaker): use Table 250.122, based on the rating of the overcurrent device (250.102(D)).
  • Metal water piping and building steel: Table 250.102(C)(1) (250.104(A)(1) and 250.104(C)). The water piping jumper never has to be larger than 3/0 copper or 250 kcmil aluminum.
  • Gas and other metal piping likely to become energized: Table 250.122, based on the circuit likely to energize it (250.104(B)).

Which jumper uses which table

Bonding jumper Size it from Based on NEC section
Main bonding jumper (service) Table 250.102(C)(1) Largest ungrounded service conductor 250.28(D)(1)
System bonding jumper (separately derived system, such as a transformer) Table 250.102(C)(1) Largest ungrounded derived conductor 250.28(D)(1)
Supply-side bonding jumper Table 250.102(C)(1) Largest ungrounded supply conductor 250.102(C)
Equipment bonding jumper, load side Table 250.122 Rating of the fuse or breaker ahead of it 250.102(D)
Interior metal water piping (service-supplied building) Table 250.102(C)(1), max 3/0 Cu or 250 kcmil Al Largest ungrounded service conductor 250.104(A)(1)
Interior metal water piping (feeder-supplied building) Table 250.122 Rating of the feeder or branch-circuit breaker 250.104(A)(3)
Exposed structural steel Table 250.102(C)(1) Largest ungrounded supply conductor 250.104(C)
Gas and other metal piping Table 250.122 Circuit likely to energize the piping 250.104(B)

The footnote under Table 250.102(C)(1) says "bonding jumper" in that table means main, system and supply-side bonding jumpers. Article 100 defines each one:

  • Supply-side bonding jumper: a conductor on the supply side of a service, inside service equipment, or for a separately derived system, that connects metal parts that must be bonded.
  • Main bonding jumper: connects the neutral (grounded conductor) to the equipment grounding conductor, the supply-side bonding jumper, or both, at the service.
  • System bonding jumper: the same connection at a separately derived system, such as a transformer.
  • Equipment bonding jumper: connects two or more portions of the equipment grounding conductor.

Table 250.102(C)(1): the copper rows you'll use most

Largest ungrounded copper conductor (or equivalent area for parallel sets) Minimum copper bonding jumper
2/0 or 3/0 AWG 4 AWG
Over 3/0 through 350 kcmil 2 AWG
Over 350 through 600 kcmil 1/0 AWG
Over 600 through 1100 kcmil 2/0 AWG
Over 1100 kcmil At least 12½% of the conductor area (Note 1)

For smaller conductors and for aluminum, read the full table in your code book. For parallel sets, add up the area of one phase (Note 3). When 12½% lands between sizes, go up to the next size that has at least that much area. Chapter 9, Table 8 lists conductor areas in circular mils (for example, 2/0 is 133,100 and 3/0 is 167,800).

Worked examples

1. Supply-side bonding jumper, one raceway

Service conductors are 4/0 copper in one raceway. 4/0 falls in the "over 3/0 through 350" row, so the supply-side bonding jumper is 2 AWG copper.

2. Parallel service in two raceways

Two raceways each carry one set of 3/0 copper (two 3/0 per phase).

  • A separate jumper for each raceway: size it from the conductors in that raceway (250.102(C)(2)). 3/0 gives 4 AWG copper per raceway.
  • One jumper bonding both raceways: use the combined area. 2 × 167,800 = 335,600 circular mils, or about 336 kcmil. That's in the "over 3/0 through 350" row, so 2 AWG copper.

3. Load-side equipment bonding jumper

The jumper bonds raceway on the load side of a 300 A breaker. Load side means Table 250.122: 4 AWG copper or 2 AWG aluminum. A single jumper for several raceways is sized from the largest overcurrent device supplying circuits in them (250.102(D)).

4. Building steel at a 400 A service

The service conductors are 500 kcmil copper. Use Table 250.102(C)(1) (250.104(C)). 500 kcmil is in the "over 350 through 600" row, so the structural steel bonding jumper is 1/0 copper.

5. Building steel at an 800 A service

Two parallel 600 kcmil copper conductors per phase: 2 × 600 = 1,200 kcmil. That's over 1100, so 12½% × 1,200 = 150 kcmil. 2/0 (133,100 circular mils) is too small, so go up to 3/0 (167,800). Answer: 3/0 copper.

6. Water piping in a building fed by a feeder

A detached shop is fed by a 100 A feeder. Its metal water piping bonds to the shop's disconnect enclosure, the equipment grounding conductor run with the feeder, or a grounding electrode. The jumper is sized from Table 250.122 (250.104(A)(3)). 100 A gives 8 AWG copper. It never has to be larger than the largest ungrounded feeder conductor.

7. Gas piping

Gas piping likely to become energized is sized by Table 250.122, using the rating of the circuit likely to energize it (250.104(B)). For a furnace on a 15 A circuit, that's 14 AWG copper, and the circuit's own equipment grounding conductor can do the job.

Installation rules that show up on exams

  • Inside or outside the raceway: both are allowed (250.102(E)).
  • Outside the raceway: no longer than 6 ft, and routed with the raceway or enclosure. Longer is allowed at outside pole locations for bonding isolated sections of metal raceway or elbows in exposed risers, and for bonding grounding electrodes (250.102(E)(2) and its Exception).
  • Water pipe and steel bonds: install them per 250.64(A), (B) and (E), and keep the points of attachment accessible (250.104(A)(1) and (C)).
  • Material: copper, aluminum, copper-clad aluminum or another corrosion-resistant material, as a wire, bus, screw or similar conductor (250.102(A)).

Check yourself

A building is supplied by a service with 3/0 copper service conductors. What size copper jumper bonds the interior metal water piping, and what size bonds exposed structural steel that is likely to become energized?

Show the answerHide the answer

4 AWG copper for both. Both use Table 250.102(C)(1) (250.104(A)(1) and 250.104(C)), and 3/0 copper falls in the "2/0 or 3/0" row.

Want more practice? Try JCR's free 25-question practice exam.

Common questions

Which NEC table sizes equipment bonding jumpers on the load side of a breaker?

Table 250.122, based on the rating of the fuse or breaker ahead of the equipment (250.102(D)).

Which table sizes a supply-side bonding jumper?

Table 250.102(C)(1), based on the largest ungrounded supply conductor or the equivalent area of a parallel set (250.102(C)(1)).

What size bonding jumper for a metal water pipe?

For a building supplied by a service, use Table 250.102(C)(1), but it never has to be larger than 3/0 copper or 250 kcmil aluminum (250.104(A)(1)). For a building supplied by a feeder or branch circuit, use Table 250.122 (250.104(A)(3)).

Which table sizes the bond to building steel at a separate building fed by a feeder?

Table 250.102(C)(1). 250.104(C) uses that table for exposed structural metal.

Which section sizes the grounded (neutral) service conductor?

250.24(C)(1) sends you to Table 250.102(C)(1). The same table sizes the main, system and supply-side bonding jumpers.

How long can a bonding jumper be outside a raceway?

No more than 6 ft, and it must be routed with the raceway or enclosure (250.102(E)(2)). The Exception allows longer jumpers at outside pole locations for exposed risers and for bonding grounding electrodes.

Written to the 2020 NEC. To follow along, pick up the 2020 NEC or open it online through a paid NFPA LiNK subscription. Our state requirements page shows the edition each state tests.

JCR checked this against the 2020 NEC in NFPA LiNK on October 29, 2026.

Related guides: Main bonding jumper size (250.28) · Equipment grounding conductor size (250.122) · Grounding electrode conductor size (250.66) · Ufer ground (concrete-encased electrode)

Free JCR grounding videos

Lock in grounding and bonding

Bonding jumper sizing is a core exam topic and a core part of JCR's self-study package, from Table 250.102(C)(1) to the parallel-conductor math.

JCR 2020 NEC self-study package with study manual and mock exam booklet

Self-study package: $495

  • 152-page JCR study manual with a six-week study plan
  • 100 video lessons (21 hours) that follow the manual
  • Realistic 500+ question mock exam (digital access and on paper)
  • Permanent code book tabs

Videos and the digital mock exam arrive by email right after you order. Printed materials ship the same or next business day.

Pick your state's package

Prefer a classroom? Exam prep workshops: two full days in Raleigh, Asheville, Mooresville (Charlotte area) or Winston-Salem. Or take the live Zoom class: four 4-hour sessions, open to any 2020 NEC exam. Includes all materials (mock exam, videos, study manual) except for NFPA 70 and 72 books. 93% pass rate for JCR classroom students.

Choose your state's self-study package

Each package is built for that state's exam and NEC edition. Pick yours:

Not sure which exam you need? See your state's license and exam requirements.

More worked examples: main bonding jumper (250.28), two ground rods and the 25-ohm rule, working space (110.26) and all NEC Answers.

Already licensed? CE classes: 8 hours, in person or on Zoom, approved in 20+ states. Our 2027 schedule includes an 8-hour Bonding & Grounding class.

  • Finished JCR's exam prep class today. It was phenomenal. Victor was our instructor. He was awesome, he keeps you engaged the entire time. I was going into my electrical exam with a good bit of anxiety and now I have a million times more confidence in passing it, after sitting thru this course for the past two days. The amount of study material and the online videos you get with the class will make you feel much more at ease going into this exam.

    Travis
    15 hours ago
  • Awesome class..learned much about power management..Victor makes it easy.Thanks, Nathan...

    William Poore
    18 hours ago
  • My husband has been going to JCR productions classes since approximately 2011 or 2012 for his CE for multiple states. They are the most comprehensive classes he could attend for that reason alone. The instructor is great and very personable. So the class doesn't drag on. I know my husband tells everyone about JCR anytime the subject of CE comes up. It is also Nice that after you complete your sign up, you receive the email with all of the information you could need in it, including the hotel. Definitely recommend.

    Cristina Jones
    a day ago
  • Mr. Ring is the most in-depth instructor I’ve had the opportunity to learn from. Top notch format kept me interested the entire session. By far the best CE class I’ve attended.

    Jeff Milhorn
    a day ago
  • Victor's class is always very informative and enjoyable to attend every year I go.

    Chase Hall
    3 weeks ago
  • Awesome Class Victor is a great instructor

    Tom P
    3 weeks ago
  • Great class. Definitely gave me the confidence to take the exam o,I didn't have before.

    Erin Lacoille
    3 weeks ago
  • It's the perfect method to ace the exam 👍

    Oly Castro
    3 weeks ago
  • Did the CEU 8-hour course with Victor. It was great. He broke down how professionals should address and use the NFPA. Thoroughly enjoyed the knowledge and experiences.

    Seth McCurty
    5 months ago
  • I have been attending JCR Productions now for 30+ years. Victor Ring and Jeff Rodriguez have instructed me from my apprenticeship days to passing my unlimited license exam. They have been a huge part of helping me to gain the knowledge I need to be successful in the electrical field. They make it fun as well. I have recommend JCR Productions for exam prep and CE courses to hundreds of people over the last 30+ years. I would not go anywhere else!

    Sean Ryan
    3 months ago
  • Victor Ring was my instructor and he did an amazing job at being very informative as well as interactive, and his concern for practicing safety was priority #1. Definitely looking forward to learning much more from this group.

    Travis Hall
    4 months ago
  • I have taken the CE classes with JCR for the last 13 years. I hold 15 state master's and 6 contractor's license and I look forward to going every year. Victor Ring is a well-educated and an excellent instructor. I would recommend this program for your CE requirements or your master's exam prep.

    terry blair
    3 months ago
  • I have enjoyed going to Victor's CEU classes since I first started attending them a few years ago. He has a lot of experience and is very knowledgeable on the NEC and in the electrical industry. I plan to do all my CEU's with JCR every year.

    Josh Boling
    6 months ago
  • I have attended JCR classes on several occasions. I used their exam prep and feel very confident in saying it was a large portion of my success. I continue to use JCR classes with Victor Ring for CE credits and have no intention of stopping in the future.

    Michael Griffin
    5 months ago
  • I completed my 8-hour Continuing Education Electrical Code course with JCR Productions and had a great experience. If you need to complete your required hours to maintain your electrical license, this course is an excellent choice. Victor Ring kept the class upbeat, engaging, and easy to follow. He does a great job breaking down the material and showing simpler, more efficient ways to navigate the NEC Code book, which makes the information practical and immediately useful in the field. Highly recommend this course to any electrician looking for a professional, informative, and enjoyable way to get their continuing education hours completed.

    Matt Pressley
    5 months ago
  • The exam prep class was great. Victor is very knowledgeable and takes making sure everyone is ready to take the test personally. Never met anyone that cares about people and how their future. I will defiantly going to taking more classes in the future.

    michael taylor
    6 months ago
  • Always learn something new from every class I have taken from JCR production. Really enjoy the way Mr Ring teaches class. Thank you ! Ken Koehler

    Ken Koehler
    3 months ago
  • Taken multiple JCR classes, specifically with Mr. Victor ring, love his classes. He’s extremely knowledgeable in his field and can present info in a way that’s easy to learn. Will continue using him for all future classes and continuing education credits.

    Brandon Whitley
    9 months ago
  • I always thoroughly enjoy the seminars with Victor Ring and JCR . Victors knowledge of the material he is teaching and his delivery is superb. Which is matched with his office staff who are very helpful.

    Robert Carignan
    7 months ago
  • Highly Recommend the Exam Preparation class!! Victor is great! I will continue using JCR in the future.

    Corey Hutchens
    6 months ago
  • I recently attended the Exam Prep Class and I was extremely impressed with Mr. Victor's approach to navigating the code book. He took what can be an intimidating book and simplified it in a way anyone could understand. He is without a doubt, the Best teacher I have had the privilege of learning from. I will be using him for my continuing education classes in the future.

    Mitch Grizzard
    5 months ago
  • This was absolutely the best class I have ever attended during my journey in the trade! Victor is awesome and extremely knowledgeable! He truly inspires you through his teaching to become the best you can be! Awesome!

    Ronald whitener
    6 months ago
  • I recently decided to go for my electrical license. Taking the JCR test prep really helped me to better understand navigating the code along with some additional methods for using the code that helped clarify the book. I will continue using JCR for my continuing ed along with other resources. Highly recommend taking this exam prep!

    Micah Barfield
    8 months ago
  • As usual Victor's class was highly enjoyable and energetic. He is a 1st rate instructor, and JCR is the only place I'll go for exam and CE studies.

    Brian Chase
    6 months ago