Supply-side bonding jumpers are sized from Table 250.102(C)(1), based on the service or supply conductors. Load-side bonding jumpers are sized from Table 250.122, based on the breaker or fuse ahead of them. Water pipe and building steel bonds also use Table 250.102(C)(1), and the water pipe bond never has to be larger than 3/0 copper. Open your 2020 NEC to Article 250, Part V and follow along.
Try this question with your code book open, then check your answer below. Questions like it are common on electrician license exams and in grounding and bonding CE quizzes.
Practice question: A service is supplied by copper conductors with an equivalent area of 2,500 kcmil per phase. What is the minimum size copper bonding jumper to the interior metal water piping?
- 2/0 AWG
- 3/0 AWG
- 300 kcmil
- 350 kcmil
Show the answerHide the answer
The answer: B, 3/0 AWG copper
- Size the water pipe bonding jumper from Table 250.102(C)(1) (250.104(A)(1)).
- 2,500 kcmil is over 1100 kcmil, so Note 1 applies: 2,500 × 12½% = 312.5 kcmil.
- But 250.104(A)(1) says this jumper never has to be larger than 3/0 copper (or 250 kcmil aluminum). 3/0 wins.
The trap is answer D. 312.5 kcmil rounds up to 350 kcmil, and that is the right size for a main or supply-side bonding jumper on this service. The water pipe jumper has its own 3/0 cap.
Want hundreds more questions like this one? JCR's $495 self-study package has 500+ practice questions (digital and printed), 100 video lessons, a 152-page study manual and permanent code tabs. Videos and the digital practice exams open right after you order.
Want a live instructor? JCR's live Zoom exam prep class teaches the 2020 NEC in four 4-hour sessions on Tuesday evenings and Saturday mornings, Eastern time, for $800. It fits any exam on the 2020 NEC. Testing in North Carolina? You can also take the two-day in-person class ($845) in Raleigh, Asheville, Mooresville (Charlotte area) or Winston-Salem. 93% pass rate for JCR classroom students.
The rule
Every bonding jumper gets its size from one of two tables. The question is which side of the overcurrent device it sits on.
- Supply side (no overcurrent device ahead of it): use Table 250.102(C)(1), based on the largest ungrounded supply conductor (250.102(C)(1)).
- Load side (after a fuse or breaker): use Table 250.122, based on the rating of the overcurrent device (250.102(D)).
- Metal water piping and building steel: Table 250.102(C)(1) (250.104(A)(1) and 250.104(C)). The water piping jumper never has to be larger than 3/0 copper or 250 kcmil aluminum.
- Gas and other metal piping likely to become energized: Table 250.122, based on the circuit likely to energize it (250.104(B)).
Which jumper uses which table
| Bonding jumper | Size it from | Based on | NEC section |
|---|---|---|---|
| Main bonding jumper (service) | Table 250.102(C)(1) | Largest ungrounded service conductor | 250.28(D)(1) |
| System bonding jumper (separately derived system, such as a transformer) | Table 250.102(C)(1) | Largest ungrounded derived conductor | 250.28(D)(1) |
| Supply-side bonding jumper | Table 250.102(C)(1) | Largest ungrounded supply conductor | 250.102(C) |
| Equipment bonding jumper, load side | Table 250.122 | Rating of the fuse or breaker ahead of it | 250.102(D) |
| Interior metal water piping (service-supplied building) | Table 250.102(C)(1), max 3/0 Cu or 250 kcmil Al | Largest ungrounded service conductor | 250.104(A)(1) |
| Interior metal water piping (feeder-supplied building) | Table 250.122 | Rating of the feeder or branch-circuit breaker | 250.104(A)(3) |
| Exposed structural steel | Table 250.102(C)(1) | Largest ungrounded supply conductor | 250.104(C) |
| Gas and other metal piping | Table 250.122 | Circuit likely to energize the piping | 250.104(B) |
The footnote under Table 250.102(C)(1) says "bonding jumper" in that table means main, system and supply-side bonding jumpers. Article 100 defines each one:
- Supply-side bonding jumper: a conductor on the supply side of a service, inside service equipment, or for a separately derived system, that connects metal parts that must be bonded.
- Main bonding jumper: connects the neutral (grounded conductor) to the equipment grounding conductor, the supply-side bonding jumper, or both, at the service.
- System bonding jumper: the same connection at a separately derived system, such as a transformer.
- Equipment bonding jumper: connects two or more portions of the equipment grounding conductor.
Table 250.102(C)(1): the copper rows you'll use most
| Largest ungrounded copper conductor (or equivalent area for parallel sets) | Minimum copper bonding jumper |
|---|---|
| 2/0 or 3/0 AWG | 4 AWG |
| Over 3/0 through 350 kcmil | 2 AWG |
| Over 350 through 600 kcmil | 1/0 AWG |
| Over 600 through 1100 kcmil | 2/0 AWG |
| Over 1100 kcmil | At least 12½% of the conductor area (Note 1) |
For smaller conductors and for aluminum, read the full table in your code book. For parallel sets, add up the area of one phase (Note 3). When 12½% lands between sizes, go up to the next size that has at least that much area. Chapter 9, Table 8 lists conductor areas in circular mils (for example, 2/0 is 133,100 and 3/0 is 167,800).
Worked examples
1. Supply-side bonding jumper, one raceway
Service conductors are 4/0 copper in one raceway. 4/0 falls in the "over 3/0 through 350" row, so the supply-side bonding jumper is 2 AWG copper.
2. Parallel service in two raceways
Two raceways each carry one set of 3/0 copper (two 3/0 per phase).
- A separate jumper for each raceway: size it from the conductors in that raceway (250.102(C)(2)). 3/0 gives 4 AWG copper per raceway.
- One jumper bonding both raceways: use the combined area. 2 × 167,800 = 335,600 circular mils, or about 336 kcmil. That's in the "over 3/0 through 350" row, so 2 AWG copper.
3. Load-side equipment bonding jumper
The jumper bonds raceway on the load side of a 300 A breaker. Load side means Table 250.122: 4 AWG copper or 2 AWG aluminum. A single jumper for several raceways is sized from the largest overcurrent device supplying circuits in them (250.102(D)).
4. Building steel at a 400 A service
The service conductors are 500 kcmil copper. Use Table 250.102(C)(1) (250.104(C)). 500 kcmil is in the "over 350 through 600" row, so the structural steel bonding jumper is 1/0 copper.
5. Building steel at an 800 A service
Two parallel 600 kcmil copper conductors per phase: 2 × 600 = 1,200 kcmil. That's over 1100, so 12½% × 1,200 = 150 kcmil. 2/0 (133,100 circular mils) is too small, so go up to 3/0 (167,800). Answer: 3/0 copper.
6. Water piping in a building fed by a feeder
A detached shop is fed by a 100 A feeder. Its metal water piping bonds to the shop's disconnect enclosure, the equipment grounding conductor run with the feeder, or a grounding electrode. The jumper is sized from Table 250.122 (250.104(A)(3)). 100 A gives 8 AWG copper. It never has to be larger than the largest ungrounded feeder conductor.
7. Gas piping
Gas piping likely to become energized is sized by Table 250.122, using the rating of the circuit likely to energize it (250.104(B)). For a furnace on a 15 A circuit, that's 14 AWG copper, and the circuit's own equipment grounding conductor can do the job.
Installation rules that show up on exams
- Inside or outside the raceway: both are allowed (250.102(E)).
- Outside the raceway: no longer than 6 ft, and routed with the raceway or enclosure. Longer is allowed at outside pole locations for bonding isolated sections of metal raceway or elbows in exposed risers, and for bonding grounding electrodes (250.102(E)(2) and its Exception).
- Water pipe and steel bonds: install them per 250.64(A), (B) and (E), and keep the points of attachment accessible (250.104(A)(1) and (C)).
- Material: copper, aluminum, copper-clad aluminum or another corrosion-resistant material, as a wire, bus, screw or similar conductor (250.102(A)).
Check yourself
A building is supplied by a service with 3/0 copper service conductors. What size copper jumper bonds the interior metal water piping, and what size bonds exposed structural steel that is likely to become energized?
Show the answerHide the answer
4 AWG copper for both. Both use Table 250.102(C)(1) (250.104(A)(1) and 250.104(C)), and 3/0 copper falls in the "2/0 or 3/0" row.
Want more practice? Try JCR's free 25-question practice exam.
Common questions
Which NEC table sizes equipment bonding jumpers on the load side of a breaker?
Table 250.122, based on the rating of the fuse or breaker ahead of the equipment (250.102(D)).
Which table sizes a supply-side bonding jumper?
Table 250.102(C)(1), based on the largest ungrounded supply conductor or the equivalent area of a parallel set (250.102(C)(1)).
What size bonding jumper for a metal water pipe?
For a building supplied by a service, use Table 250.102(C)(1), but it never has to be larger than 3/0 copper or 250 kcmil aluminum (250.104(A)(1)). For a building supplied by a feeder or branch circuit, use Table 250.122 (250.104(A)(3)).
Which table sizes the bond to building steel at a separate building fed by a feeder?
Table 250.102(C)(1). 250.104(C) uses that table for exposed structural metal.
Which section sizes the grounded (neutral) service conductor?
250.24(C)(1) sends you to Table 250.102(C)(1). The same table sizes the main, system and supply-side bonding jumpers.
How long can a bonding jumper be outside a raceway?
No more than 6 ft, and it must be routed with the raceway or enclosure (250.102(E)(2)). The Exception allows longer jumpers at outside pole locations for exposed risers and for bonding grounding electrodes.
Written to the 2020 NEC. To follow along, pick up the 2020 NEC or open it online through a paid NFPA LiNK subscription. Our state requirements page shows the edition each state tests.
JCR checked this against the 2020 NEC in NFPA LiNK on October 29, 2026.
Related guides: Main bonding jumper size (250.28) · Equipment grounding conductor size (250.122) · Grounding electrode conductor size (250.66) · Ufer ground (concrete-encased electrode)
Free JCR grounding videos
- Bonding and grounding explained (Article 250)
- How to size the equipment grounding conductor (250.122)
- See more on JCR's YouTube channel
Lock in grounding and bonding
Bonding jumper sizing is a core exam topic and a core part of JCR's self-study package, from Table 250.102(C)(1) to the parallel-conductor math.
Self-study package: $495
- 152-page JCR study manual with a six-week study plan
- 100 video lessons (21 hours) that follow the manual
- Realistic 500+ question mock exam (digital access and on paper)
- Permanent code book tabs
Videos and the digital mock exam arrive by email right after you order. Printed materials ship the same or next business day.
Prefer a classroom? Exam prep workshops: two full days in Raleigh, Asheville, Mooresville (Charlotte area) or Winston-Salem. Or take the live Zoom class: four 4-hour sessions, open to any 2020 NEC exam. Includes all materials (mock exam, videos, study manual) except for NFPA 70 and 72 books. 93% pass rate for JCR classroom students.
Choose your state's self-study package
Each package is built for that state's exam and NEC edition. Pick yours:
Not sure which exam you need? See your state's license and exam requirements.
More worked examples: main bonding jumper (250.28), two ground rods and the 25-ohm rule, working space (110.26) and all NEC Answers.