Exam question: main bonding jumper size for 8 parallel sets of 500 kcmil copper

This question is from JCR's 500+ question mock exam. 47% of students got this wrong. Try it with your 2020 NEC open, then check your answer below.

Show the answerHide the answer

The answer: D, 500 kcmil

  • 8 sets of 500 kcmil copper in parallel: 8 × 500 = 4,000 kcmil.
  • That is over 1100 kcmil, so Note 1's 12½% rule applies: 4,000 × 12½% = 500 kcmil copper.

The most common wrong answer was 1/0. That is the table row for a single 500 kcmil conductor. The question has eight of them per phase, 4,000 kcmil in all.

Want hundreds more questions like this one? JCR's $495 self-study package has 500+ practice questions (digital and printed), 100 video lessons, a 152-page study manual and permanent code tabs. Videos and the digital practice exams open right after you order.

Pick your state's package

Testing in North Carolina? Take JCR's NC exam prep class: two full days in person ($845) in Raleigh, Asheville, Mooresville (Charlotte area) or Winston-Salem, or live on Zoom on Tuesday evenings and Saturday mornings. 93% pass rate for JCR classroom students.

See NC class dates

The rule

  • Where the bond goes: at a service, the grounded conductor (neutral) is bonded to the equipment grounding conductors and the service-disconnect enclosure by an unspliced main bonding jumper inside the enclosure, not on the load side.
  • Size: use Table 250.102(C)(1), based on the largest ungrounded service conductor.
  • Large services: above 1100 kcmil copper (1750 kcmil aluminum), the jumper must be at least 12½% of the area of that conductor, or of the parallel set.

Where the bond goes

  • At the service. The grounding electrode conductor connects to the grounded service conductor at any accessible point from the load end of the overhead service conductors, service drop, underground service conductors, or service lateral, up to and including the terminal or bus where the grounded service conductor lands at the service disconnecting means (250.24(A)(1)).
  • Not downstream. On the load side of the service disconnect, the grounded conductor may not be connected to normally non-current-carrying metal parts or to equipment grounding conductors, or be reconnected to ground, unless Article 250 permits it (250.24(A)(5)). The Informational Note points to 250.30 (separately derived systems), 250.32 (separate buildings or structures) and 250.142.
  • Main bonding jumper required. An unspliced main bonding jumper connects the equipment grounding conductor(s) and the service-disconnect enclosure to the grounded conductor within the enclosure for each service disconnect (250.24(B)).
  • Bring the neutral to the service. Where an ac system of 1000 V or less is grounded at any point, the grounded conductor must be run with the ungrounded conductors to each service disconnecting means and connected there (250.24(C)). Size it from Table 250.102(C)(1). In parallel in two or more raceways or cables, it can't be smaller than 1/0 AWG (250.24(C)(2)).

The jumper can be copper, aluminum, copper-clad aluminum or another corrosion-resistant material, and it can be a wire, bus, screw or similar conductor (250.28(A)). A screw used alone as the main bonding jumper must have a green finish that is visible with the screw installed (250.28(B)).

How to size it

Find the largest ungrounded service conductor, then read Table 250.102(C)(1) (250.28(D)(1)). The two copper rows the examples below use:

Largest ungrounded copper conductor (or equivalent area for parallel conductors) Minimum copper bonding jumper
2/0 or 3/0 AWG 4 AWG
Over 1100 kcmil 12½% of the conductor area (Note 1)

For every other size, and for aluminum, read Table 250.102(C)(1) in your code book.

For parallel conductors, use the combined area of the conductors in one phase. The table's first column and Note 1 both work from this equivalent area.

Note 1 says the jumper's area can't be less than 12½%, so if the result lands between sizes, go to the next larger size. It also never has to be larger than the largest ungrounded conductor or set.

Worked examples

  • 3/0 copper service conductors: main bonding jumper = 4 AWG copper.
  • 4 sets of 500 kcmil copper in parallel: 4 × 500 = 2,000 kcmil. Over 1100, so 2,000 × 12½% = 250 kcmil copper.
  • 8 sets of 500 kcmil copper in parallel (the exam question above): 8 × 500 = 4,000 kcmil. 4,000 × 12½% = 500 kcmil copper.

Aluminum service conductors

Table 250.102(C)(1) has a separate column for aluminum or copper-clad aluminum. With 4/0 aluminum service conductors, the minimum main bonding jumper is 2 AWG aluminum or 4 AWG copper. With 500 kcmil aluminum, it's 1/0 aluminum or 2 AWG copper.

Above 1750 kcmil aluminum, Note 1's 12½% rule applies to an aluminum jumper. For a copper jumper on aluminum conductors, use Note 2: take 12½% of the copper conductors that would have the same ampacity.

Check yourself

For a 120/240 V single-phase dwelling service, is either of these allowed?

  1. The service conductors don't include a grounded conductor.
  2. The grounding connection is made on the load side of the service disconnect.
Show the answerHide the answer

Neither. 250.24(C) requires the grounded conductor to be brought to the service, and 250.24(A)(5) prohibits the load-side connection.

Want more practice? Try JCR's free 25-question practice exam.

Common questions

Where is the neutral bonded to ground?

At the service. The main bonding jumper inside each service disconnect enclosure bonds the neutral to the enclosure and the equipment grounding conductors (250.24(B)). The grounding electrode conductor can connect to the neutral anywhere from the load end of the service drop or lateral up to the service disconnect (250.24(A)(1)). On the load side of the service disconnect, the neutral stays separate from the equipment grounding conductors, except where Article 250 allows otherwise.

What size main bonding jumper for 2/0 copper service conductors?

4 AWG copper. Table 250.102(C)(1) puts 2/0 and 3/0 copper in the same row.

Can a screw be the main bonding jumper?

Yes. A screw used by itself as the main bonding jumper must have a green finish that you can see with the screw installed (250.28(B)).

Main bonding jumper vs. system bonding jumper: what's the difference?

Both connect the neutral (grounded conductor) to the equipment grounding conductor. The main bonding jumper does it at the service (250.24(B)). The system bonding jumper does it at a separately derived system, a power source other than the service (250.30(A)(1)). Both follow 250.28 for material, the green screw and sizing.

Written to the 2020 NEC. To follow along, pick up the 2020 NEC or open it online through a paid NFPA LiNK subscription. Our state requirements page shows the edition each state tests.

JCR checked this against the 2020 NEC in NFPA LiNK on October 21, 2026.

Related guides: Dwelling service load calculation, step by step · The 5 most-missed questions on JCR's free practice exam

Free JCR grounding videos

Lock in grounding and bonding

Grounding and bonding is a core exam topic, and a core part of JCR's self-study package, from the tables to the parallel-conductor math.

JCR 2020 NEC self-study package with study manual and mock exam booklet

Self-study package: $495

  • 152-page JCR study manual with a six-week study plan
  • 100 video lessons (21 hours) that follow the manual
  • Realistic 500+ question mock exam (digital access and on paper)
  • Permanent code book tabs

Videos and the digital mock exam arrive by email right after you order. Printed materials ship the same business day.

Pick your state's package

Prefer a classroom? Exam prep workshops: two full days in Raleigh, Asheville, Mooresville (Charlotte area), Winston-Salem, or live on Zoom. Includes all materials (mock exam, videos, study manual) except for NFPA 70 and 72 books. 93% pass rate for JCR classroom students.

Choose your state's self-study package

Each package is built for that state's exam and NEC edition. Pick yours:

Not sure which exam you need? See your state's license and exam requirements.

More worked examples: grounding electrode conductor size (Table 250.66), equipment grounding conductor size (Table 250.122), working space at service equipment (110.26) and all NEC Answers.

Already licensed? CE classes: 8 hours, in person or on Zoom, approved in 20+ states. Our 2027 schedule includes an 8-hour Bonding & Grounding class.